The project was making (300) piles in the ground to a depth of 20 meters and then filled with gravel and individual layer of gravel over the entire basin followed by a membrane layer then a final layer of sand to filter the water, this is to increase the capacity to (70) thousand cubic meters of rain water per day.The project also includes extension pipelines to drain rainwater from the intersection of Jaffa line and Dura to the park to solve the problem of water harvesting in the intersection
LOCATION : Gaza City
STATUS : Done Finished in:2016
BUDGET : 20400
CLIENT : Gaza Municipality
DONOR :
ENFRA RESPONSIBILITIES :
Supervision of all project activities including daily supervision, Reporting, payment approval, variation order